BetaActiveSolarSPPLBNL + Live
52.2 MW generation in Benton, AR · In queue since May 2017 · Proposed COD December 2024
52.2 MW
Capacity
1
Components
Solar
8y 10m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
7y 7m
Schedule
16 months past proposed COD
Construction75%
Queue EntryMay 28, 2017
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
AR
County
Benton
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Chamber Springs 161kV sub
Data Source
LBNL + Live