— Project Summary

Queue ID
SPP-GEN-2017-076
Capacity
52.2 MW
Technology
Solar
Status
active
Location
Benton, AR
Region
SPP
Developer
IA Status
IA Executed

BetaActiveSolarSPPLBNL + Live

52.2 MW generation in Benton, AR · In queue since May 2017 · Proposed COD December 2024

52.2 MW

Capacity

1

Components

Solar

8y 10m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

7y 7m

Schedule

16 months past proposed COD

Construction75%
Queue EntryMay 28, 2017

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2024-12-01

Project Details

State

AR

County

Benton

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Chamber Springs 161kV sub

Data Source

LBNL + Live

No news available for this project.