BetaActiveWindSPPLBNL + Live
300 MW generation in Williams, ND · In queue since May 2017 · Proposed COD December 2026
300 MW
Capacity
1
Components
Wind
8y 10m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 7m
Construction75%
Queue EntryMay 31, 2017
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
ND
County
Williams
Region
SPP
Developer
—
Utility
BEPC
Entity
SPP
Point of Interconnection
Neset 230 kV Substation
Data Source
LBNL + Live
No news available for this project.