BetaActiveWindSPPLBNL + Live
151.2 MW generation in Dekalb, MO · In queue since August 2016 · Proposed COD October 2021
151.2 MW
Capacity
1
Components
Wind
9y 7m
In Queue
Withdrawn
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
5y 2m
Schedule
54 months past proposed COD
In Study38%
Queue EntryAug 11, 2016
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-10-29
Project Details
State
MO
County
Dekalb
Region
SPP
Developer
—
Utility
KCPL
Entity
SPP
Point of Interconnection
Mullen Creek-Sibley (Ketchum) 345kV
Data Source
LBNL + Live
No news available for this project.