BetaActiveWindSPPLBNL + Live
200 MW generation in Johnston, OK · In queue since March 2016 · Proposed COD June 2023
200 MW
Capacity
1
Components
Wind
10 years
In Queue
Withdrawn
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
7y 3m
Schedule
34 months past proposed COD
In Study38%
Queue EntryMar 30, 2016
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
OK
County
Johnston
Region
SPP
Developer
—
Utility
OGE
Entity
SPP
Point of Interconnection
Hugo-Sunnyside 345 kV
Data Source
LBNL + Live
No news available for this project.