BetaActiveWindSPPLBNL + Live
78.2 MW generation in Edwards, KS · In queue since March 2016 · Proposed COD December 2023
78.2 MW
Capacity
1
Components
Wind
10 years
In Queue
Withdrawn
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
7y 9m
Schedule
28 months past proposed COD
In Study38%
Queue EntryMar 29, 2016
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
KS
County
Edwards
Region
SPP
Developer
—
Utility
MIDW
Entity
SPP
Point of Interconnection
North Kinsley 115 kV
Data Source
LBNL + Live
No news available for this project.