100.05 MW generation in Barnes, ND · In queue since March 2016 · Proposed COD December 2024
100.05 MW
Capacity
1
Components
Wind
10 years
In Queue
Withdrawn
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
8y 9m
Schedule
15 months past proposed COD
In Study38%
Queue EntryMar 28, 2016
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
ND
County
Barnes
Region
SPP
Developer
—
Utility
WAPA
Entity
SPP
Point of Interconnection
Valley City 115 kV
Data Source
LBNL + Live