— Project Summary

Queue ID
SPP-GEN-2015-095
Capacity
176 MW
Technology
Wind
Status
active
Location
Woods, OK
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

176 MW generation in Woods, OK · In queue since September 2015 · Proposed COD June 2020

176 MW

Capacity

1

Components

Wind

10y 6m

In Queue

Withdrawn

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

4y 9m

Schedule

71 months past proposed COD

In Study38%
Queue EntrySep 21, 2015

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-06-01

Project Details

State

OK

County

Woods

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Tap Mooreland - Knob Hill 138kV

Data Source

LBNL + Live

No news available for this project.