— Project Summary

Queue ID
SPP-GEN-2015-093
Capacity
250 MW
Technology
Wind
Status
active
Location
Caddo, OK
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

250 MW generation in Caddo, OK · In queue since September 2015 · Proposed COD December 2025

250 MW

Capacity

1

Components

Wind

10y 6m

In Queue

Withdrawn

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

10y 3m

Schedule

3 months past proposed COD

In Study38%
Queue EntrySep 29, 2015

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

OK

County

Caddo

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Gracemont 345kV

Data Source

LBNL + Live

No news available for this project.