BetaActiveWindSPPLBNL + Live
250 MW generation in Caddo, OK · In queue since September 2015 · Proposed COD December 2025
250 MW
Capacity
1
Components
Wind
10y 6m
In Queue
Withdrawn
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
10y 3m
Schedule
3 months past proposed COD
In Study38%
Queue EntrySep 29, 2015
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
OK
County
Caddo
Region
SPP
Developer
—
Utility
OGE
Entity
SPP
Point of Interconnection
Gracemont 345kV
Data Source
LBNL + Live
No news available for this project.