— Project Summary

Queue ID
SPP-GEN-2015-087
Capacity
66 MW
Technology
Wind
Status
active
Location
Thayer, NE
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

66 MW generation in Thayer, NE · In queue since September 2015 · Proposed COD December 2019

66 MW

Capacity

1

Components

Wind

10y 6m

In Queue

Withdrawn

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

4y 3m

Schedule

77 months past proposed COD

In Study38%
Queue EntrySep 30, 2015

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-12-01

Project Details

State

NE

County

Thayer

Region

SPP

Developer

Utility

NPPD

Entity

SPP

Point of Interconnection

Hebron-Fairbury 115 kV

Data Source

LBNL + Live

No news available for this project.