— Project Summary

Queue ID
SPP-GEN-2015-071
Capacity
200 MW
Technology
Wind
Status
active
Location
Beckham, OK
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

200 MW generation in Beckham, OK · In queue since October 2015 · Proposed COD December 2021

200 MW

Capacity

1

Components

Wind

10y 5m

In Queue

Withdrawn

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

6y 2m

Schedule

52 months past proposed COD

In Study38%
Queue EntryOct 9, 2015

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

OK

County

Beckham

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Chisholm 345kV

Data Source

LBNL + Live

No news available for this project.