BetaActiveSolarSPPLBNL + Live
40 MW generation in Beckham, OK · In queue since October 2015 · Proposed COD December 2024
40 MW
Capacity
1
Components
Solar
10y 5m
In Queue
Withdrawn
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
9y 2m
Schedule
16 months past proposed COD
In Study38%
Queue EntryOct 6, 2015
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
OK
County
Beckham
Region
SPP
Developer
—
Utility
WFEC
Entity
SPP
Point of Interconnection
Erick 138kV Substation
Data Source
LBNL + Live