— Project Summary

Queue ID
SPP-GEN-2015-029
Capacity
161 MW
Technology
Wind
Status
active
Location
Dewey, OK
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

161 MW generation in Dewey, OK · In queue since March 2015 · Proposed COD December 2020

161 MW

Capacity

1

Components

Wind

11 years

In Queue

Withdrawn

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

5y 9m

Schedule

65 months past proposed COD

In Study38%
Queue EntryMar 31, 2015

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-12-01

Project Details

State

OK

County

Dewey

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Tatonga 345kV

Data Source

LBNL + Live

No news available for this project.