BetaActiveWindSPPLBNL + Live
161 MW generation in Dewey, OK · In queue since March 2015 · Proposed COD December 2020
161 MW
Capacity
1
Components
Wind
11 years
In Queue
Withdrawn
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
5y 9m
Schedule
65 months past proposed COD
In Study38%
Queue EntryMar 31, 2015
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-01
Project Details
State
OK
County
Dewey
Region
SPP
Developer
—
Utility
OGE
Entity
SPP
Point of Interconnection
Tatonga 345kV
Data Source
LBNL + Live
No news available for this project.