— Project Summary

Queue ID
SPP-GEN-2014-003
Capacity
15.8 MW
Technology
Wind
Status
active
Location
Blaine, OK
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

15.8 MW generation in Blaine, OK · In queue since February 2014 · Proposed COD December 2014

15.8 MW

Capacity

1

Components

Wind

12y 1m

In Queue

Withdrawn

IA Status

COD target: 2014

Interconnection Timeline

Total Duration

10 months

Schedule

137 months past proposed COD

In Study38%
Queue EntryFeb 19, 2014

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-12-31

Project Details

State

OK

County

Blaine

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Tatonga 345kV

Data Source

LBNL + Live

No news available for this project.