BetaActiveWindSPPLBNL + Live
15.8 MW generation in Blaine, OK · In queue since February 2014 · Proposed COD December 2014
15.8 MW
Capacity
1
Components
Wind
12y 1m
In Queue
Withdrawn
IA Status
COD target: 2014
Interconnection Timeline
Total Duration
10 months
Schedule
137 months past proposed COD
In Study38%
Queue EntryFeb 19, 2014
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2014-12-31
Project Details
State
OK
County
Blaine
Region
SPP
Developer
—
Utility
OGE
Entity
SPP
Point of Interconnection
Tatonga 345kV
Data Source
LBNL + Live
No news available for this project.