— Project Summary

Queue ID
SPP-GEN-2013-030
Capacity
300 MW
Technology
Wind
Status
active
Location
Ochiltree, TX
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

300 MW generation in Ochiltree, TX · In queue since September 2013 · Proposed COD December 2020

300 MW

Capacity

1

Components

Wind

12y 6m

In Queue

Withdrawn

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

7y 3m

Schedule

64 months past proposed COD

In Study38%
Queue EntrySep 30, 2013

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-12-31

Project Details

State

TX

County

Ochiltree

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Hitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV

Data Source

LBNL + Live

No news available for this project.