BetaActiveWindSPPLBNL + Live
300 MW generation in Ochiltree, TX · In queue since September 2013 · Proposed COD December 2020
300 MW
Capacity
1
Components
Wind
12y 6m
In Queue
Withdrawn
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
7y 3m
Schedule
64 months past proposed COD
In Study38%
Queue EntrySep 30, 2013
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-31
Project Details
State
TX
County
Ochiltree
Region
SPP
Developer
—
Utility
OGE
Entity
SPP
Point of Interconnection
Hitchland-Woodward EHV Dbl Ckt (Beaver County) 345kV
Data Source
LBNL + Live
No news available for this project.