BetaActiveWindSPPLBNL + Live
136 MW generation in Osage, OK · In queue since September 2012
136 MW
Capacity
1
Components
Wind
13y 6m
In Queue
Withdrawn
IA Status
Interconnection Timeline
Total Duration
13y 6m
In Study38%
Queue EntrySep 28, 2012
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
OK
County
Osage
Region
SPP
Developer
—
Utility
AEP
Entity
SPP
Point of Interconnection
Shidler 138kV
Data Source
LBNL + Live
No news available for this project.