— Project Summary

Queue ID
SPP-GEN-2011-049
Capacity
250.7 MW
Technology
Wind
Status
active
Location
Beckham, OK
Region
SPP
Developer
IA Status
Withdrawn

BetaActiveWindSPPLBNL + Live

250.7 MW generation in Beckham, OK · In queue since September 2011 · Proposed COD July 2020

250.7 MW

Capacity

1

Components

Wind

14y 6m

In Queue

Withdrawn

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

8y 10m

Schedule

69 months past proposed COD

In Study38%
Queue EntrySep 30, 2011

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-07-31

Project Details

State

OK

County

Beckham

Region

SPP

Developer

Utility

OGE

Entity

SPP

Point of Interconnection

Border 345kV

Data Source

LBNL + Live

No news available for this project.