BetaActiveWindSPPLBNL + Live
250.7 MW generation in Beckham, OK · In queue since September 2011 · Proposed COD July 2020
250.7 MW
Capacity
1
Components
Wind
14y 6m
In Queue
Withdrawn
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
8y 10m
Schedule
69 months past proposed COD
In Study38%
Queue EntrySep 30, 2011
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-07-31
Project Details
State
OK
County
Beckham
Region
SPP
Developer
—
Utility
OGE
Entity
SPP
Point of Interconnection
Border 345kV
Data Source
LBNL + Live