BetaActiveWindSPPLBNL + Live
200.1 MW generation in Hodgeman, KS · In queue since March 2010
200.1 MW
Capacity
1
Components
Wind
16 years
In Queue
Withdrawn
IA Status
Interconnection Timeline
Total Duration
16 years
In Study38%
Queue EntryMar 31, 2010
Interconnection request submitted to ISO/RTO
DISIS StudyCurrent
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
KS
County
Hodgeman
Region
SPP
Developer
—
Utility
SUNC
Entity
SPP
Point of Interconnection
Spearville 345kV
Data Source
LBNL + Live
No news available for this project.