— Project Summary

Queue ID
SPP-ERAS-2025-033
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Dodge City, KS
Region
SPP
Developer
IA Status

BetaActiveHybrid / Solar/StorageSPPLive · SPP

150 MW generation in Dodge City, KS · In queue since October 2025

150 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

KS

County

Dodge City

Region

SPP

Developer

Utility

SEPC

Entity

SPP

Point of Interconnection

Fort Dodge 115 kV Substation

Data Source

Live · SPP

No news available for this project.