— Project Summary

Queue ID
SPP-ERAS-2025-026
Capacity
744 MW
Technology
Gas
Status
active
Location
Lawton, OK
Region
SPP
Developer
IA Status

BetaActiveThermal / Combined CycleSPPLive · SPP

744 MW generation in Lawton, OK · In queue since October 2025

744 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 2, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Lawton

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Oklaunion-Lawton East Side 345kV Line

Data Source

Live · SPP

No news available for this project.