— Project Summary

Queue ID
SPP-ERAS-2025-024
Capacity
744 MW
Technology
Gas
Status
active
Location
Lawton, OK
Region
SPP
Developer
IA Status

BetaActiveThermal / Combined CycleSPPLive · SPP

744 MW generation in Lawton, OK · In queue since October 2025

744 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 2, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Lawton

Region

SPP

Developer

Utility

AEP

Entity

SPP

Point of Interconnection

Comanche 138kV Substation

Data Source

Live · SPP

No news available for this project.