BetaActiveBattery/Storage / BatterySPPLive · SPP
123 MW storage in Ada, OK · In queue since October 2025
123 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
5 months
Pre-Study0%
Queue EntryOct 1, 2025
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
OK
County
Ada
Region
SPP
Developer
—
Utility
PEC
Entity
SPP
Point of Interconnection
Monte Vista 138 kV Substation
Data Source
Live · SPP