— Project Summary

Queue ID
SPP-ERAS-2025-022
Capacity
123 MW
Technology
Battery
Status
active
Location
Ada, OK
Region
SPP
Developer
IA Status

BetaActiveBattery/Storage / BatterySPPLive · SPP

123 MW storage in Ada, OK · In queue since October 2025

123 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

OK

County

Ada

Region

SPP

Developer

Utility

PEC

Entity

SPP

Point of Interconnection

Monte Vista 138 kV Substation

Data Source

Live · SPP

No news available for this project.