— Project Summary

Queue ID
SPP-ERAS-2025-021
Capacity
500 MW
Technology
Wind
Status
active
Location
Hale Center, TX
Region
SPP
Developer
IA Status

BetaActiveWind / WindSPPLive · SPP

500 MW generation in Hale Center, TX · In queue since October 2025

500 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 2, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

TX

County

Hale Center

Region

SPP

Developer

Utility

SPS

Entity

SPP

Point of Interconnection

Border-Tuco 345kV Line

Data Source

Live · SPP

No news available for this project.