— Project Summary

Queue ID
SPP-ERAS-2025-020
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
Lovington, NM
Region
SPP
Developer
IA Status

BetaActiveHybrid / Solar/StorageSPPLive · SPP

400 MW generation in Lovington, NM · In queue since October 2025

400 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 2, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NM

County

Lovington

Region

SPP

Developer

Utility

SPS

Entity

SPP

Point of Interconnection

Hobbs - Yoakum 345 kV Line

Data Source

Live · SPP