450.6 MW generation in Maryville, MO · In queue since September 2025
450.6 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Interconnection Timeline
Total Duration
6 months
Pre-Study0%
Queue EntrySep 30, 2025
Interconnection request submitted to ISO/RTO
DISIS Study
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MO
County
Maryville
Region
SPP
Developer
—
Utility
WERE
Entity
SPP
Point of Interconnection
Mullin Creek 345 kV Substation
Data Source
Live · SPP