— Project Summary

Queue ID
SPP-ERAS-2025-007
Capacity
450.6 MW
Technology
Gas
Status
active
Location
Maryville, MO
Region
SPP
Developer
IA Status

BetaActiveThermal / Combustion TurbineSPPLive · SPP

450.6 MW generation in Maryville, MO · In queue since October 2025

450.6 MW

Capacity

0

Components

5 months

In Queue

IA Status

Interconnection Timeline

Total Duration

5 months

Pre-Study0%
Queue EntryOct 2, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

MO

County

Maryville

Region

SPP

Developer

Utility

WERE

Entity

SPP

Point of Interconnection

Mullin Creek 345 kV Substation

Data Source

Live · SPP

No news available for this project.