BetaActiveSolarBatterySOCOLBNL
160 MW hybrid in Baldwin, AL · In queue since December 2021 · Proposed COD December 2026
160 MW
Capacity
2
Components
Solar + Battery
4y 3m
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5 years
In Study38%
Queue EntryDec 3, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-03
Technology
Solar80 MW · 50%
Battery80 MW · 50%
Project Details
State
AL
County
Baldwin
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Elsanor - Mobile Hwy (GULF) 230 kV Line
Data Source
LBNL
No news available for this project.