— Project Summary

Queue ID
SOCO-IC-994
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Toombs, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

300 MW hybrid in Toombs, GA · In queue since November 2021 · Proposed COD April 2025

300 MW

Capacity

2

Components

Solar + Battery

4y 4m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 5m

Schedule

11 months past proposed COD

In Study38%
Queue EntryNov 12, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-30

Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details

State

GA

County

Toombs

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Hatch - Vidalia 230 kV Line

Data Source

LBNL

No news available for this project.