200 MW generation in Toombs, GA · In queue since October 2021 · Proposed COD April 2025
200 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 6m
Schedule
11 months past proposed COD
In Study38%
Queue EntryOct 21, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-04-30
Project Details
State
GA
County
Toombs
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Hatch - Vidalia 230 kV Line
Data Source
LBNL