80 MW generation in Dale, AL · In queue since July 2021 · Proposed COD October 2025
80 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 3m
Schedule
6 months past proposed COD
In Study38%
Queue EntryJul 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
AL
County
Dale
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Pinckard _x0013_ Pike County 230 kV Line
Data Source
LBNL