— Project Summary

Queue ID
SOCO-IC-974
Capacity
600 MW
Technology
Battery
Status
active
Location
Fulton, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveBatterySOCOLBNL

600 MW storage in Fulton, GA · In queue since July 2021 · Proposed COD June 2025

600 MW

Capacity

1

Components

Battery

4y 8m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 11m

Schedule

9 months past proposed COD

In Study38%
Queue EntryJul 19, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-15

Project Details

State

GA

County

Fulton

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

East Point - Union City (White) 230 kV Line

Data Source

LBNL

No news available for this project.