BetaActiveBatterySOCOLBNL
600 MW storage in Fulton, GA · In queue since July 2021 · Proposed COD June 2025
600 MW
Capacity
1
Components
Battery
4y 8m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 11m
Schedule
9 months past proposed COD
In Study38%
Queue EntryJul 19, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-15
Project Details
State
GA
County
Fulton
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
East Point - Union City (White) 230 kV Line
Data Source
LBNL
No news available for this project.