— Project Summary

Queue ID
SOCO-IC-972
Capacity
250 MW
Technology
Solar
Status
active
Location
Jasper, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

250 MW generation in Jasper, GA · In queue since July 2021 · Proposed COD August 2024

250 MW

Capacity

1

Components

Solar

4y 8m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 1m

Schedule

19 months past proposed COD

In Study38%
Queue EntryJul 14, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-08-21

Project Details

State

GA

County

Jasper

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Eatonton Primary - Porterdale Primary 230 kV Line

Data Source

LBNL

No news available for this project.