— Project Summary

Queue ID
SOCO-IC-966
Capacity
130 MW
Technology
Solar+Battery
Status
active
Location
Decatur, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

130 MW hybrid in Decatur, GA · In queue since June 2021 · Proposed COD July 2024

130 MW

Capacity

1

Components

Solar

4y 9m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 1m

Schedule

21 months past proposed COD

In Study38%
Queue EntryJun 9, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-07-15

Project Details

State

GA

County

Decatur

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

South Bainbridge - Sub 20 (TAL) 230 kV Line

Data Source

LBNL

No news available for this project.