150 MW hybrid in Emanuel, GA · In queue since June 2021 · Proposed COD July 2025
150 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 1m
Schedule
8 months past proposed COD
In Study38%
Queue EntryJun 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-07-15
Project Details
State
GA
County
Emanuel
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Vidalia - Wadley Primary (Black) 230 kV Line
Data Source
LBNL