88 MW hybrid in Lowndes, AL · In queue since April 2021 · Proposed COD June 2026
88 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 2m
In Study38%
Queue EntryApr 20, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Technology
Solar58 MW · 66%
Battery30 MW · 34%
Project Details
State
AL
County
Lowndes
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Greenville - Pintlala 115 kV Line
Data Source
LBNL