— Project Summary

Queue ID
SOCO-IC-955
Capacity
88 MW
Technology
Solar+Battery
Status
active
Location
Lowndes, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

88 MW hybrid in Lowndes, AL · In queue since April 2021 · Proposed COD June 2026

88 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 2m

In Study38%
Queue EntryApr 20, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Technology
Solar58 MW · 66%
Battery30 MW · 34%
Project Details

State

AL

County

Lowndes

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Greenville - Pintlala 115 kV Line

Data Source

LBNL

No news available for this project.