— Project Summary

Queue ID
SOCO-IC-952
Capacity
150 MW
Technology
Battery
Status
active
Location
Polk, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveBatterySOCOLBNL

150 MW storage in Polk, GA · In queue since April 2021 · Proposed COD November 2024

150 MW

Capacity

1

Components

Battery

4y 11m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 7m

Schedule

17 months past proposed COD

In Study38%
Queue EntryApr 6, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-11-01

Project Details

State

GA

County

Polk

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Portland TS 115 kV Bus

Data Source

LBNL

No news available for this project.