150 MW storage in Polk, GA · In queue since April 2021 · Proposed COD November 2024
150 MW
Capacity
1
Components
Battery
4y 11m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 7m
Schedule
17 months past proposed COD
In Study38%
Queue EntryApr 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-01
Project Details
State
GA
County
Polk
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Portland TS 115 kV Bus
Data Source
LBNL