— Project Summary

Queue ID
SOCO-IC-950
Capacity
250 MW
Technology
Solar
Status
active
Location
Mcduffie, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

250 MW generation in Mcduffie, GA · In queue since April 2021 · Proposed COD June 2024

250 MW

Capacity

1

Components

Solar

4y 11m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 2m

Schedule

22 months past proposed COD

Construction75%
Queue EntryApr 6, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2024-06-01

Project Details

State

GA

County

Mcduffie

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Thomson Primary Substation 230 kV Bus

Data Source

LBNL

No news available for this project.