BetaActiveSolarSOCOLBNL
250 MW generation in Mcduffie, GA · In queue since April 2021 · Proposed COD June 2024
250 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 2m
Schedule
22 months past proposed COD
Construction75%
Queue EntryApr 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
GA
County
Mcduffie
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Thomson Primary Substation 230 kV Bus
Data Source
LBNL
No news available for this project.