— Project Summary

Queue ID
SOCO-IC-945
Capacity
270 MW
Technology
Solar+Battery
Status
active
Location
Turner, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

270 MW hybrid in Turner, GA · In queue since April 2021 · Proposed COD February 2026

270 MW

Capacity

2

Components

Solar + Battery

4y 11m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 10m

Schedule

2 months past proposed COD

In Study38%
Queue EntryApr 6, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-01

Technology
Solar210 MW · 78%
Battery60 MW · 22%
Project Details

State

GA

County

Turner

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Tifton - Pitts 230 kV Line

Data Source

LBNL