BetaActiveSolarSOCOLBNL
210 MW generation in Turner, GA · In queue since April 2021 · Proposed COD February 2026
210 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 10m
Schedule
2 months past proposed COD
In Study38%
Queue EntryApr 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-01
Project Details
State
GA
County
Turner
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Tifton - Pitts 230 kV Line
Data Source
LBNL
No news available for this project.