— Project Summary

Queue ID
SOCO-IC-943
Capacity
80 MW
Technology
Solar
Status
active
Location
Talladega, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

80 MW generation in Talladega, AL · In queue since March 2021 · Proposed COD April 2025

80 MW

Capacity

1

Components

Solar

5 years

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 1m

Schedule

11 months past proposed COD

In Study38%
Queue EntryMar 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-16

Project Details

State

AL

County

Talladega

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Coosa Pines - Logan Martin Dam No. 2 115 kV Line

Data Source

LBNL