BetaActiveSolarBatterySOCOLBNL
1,600 MW hybrid in Glynn, GA · In queue since March 2021 · Proposed COD April 2025
1,600 MW
Capacity
2
Components
Solar + Battery
5 years
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 1m
Schedule
12 months past proposed COD
In Study38%
Queue EntryMar 19, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-04-14
Technology
Solar1,200 MW · 75%
Battery400 MW · 25%
Project Details
State
GA
County
Glynn
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Thalmann TS 500 kV Bus
Data Source
LBNL
No news available for this project.