BetaActiveSolarBatterySOCOLBNL
170 MW hybrid in Perry, MS · In queue since March 2021 · Proposed COD January 2024
170 MW
Capacity
2
Components
Solar + Battery
5 years
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 10m
Schedule
27 months past proposed COD
In Study38%
Queue EntryMar 18, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-01-15
Technology
Solar110 MW · 65%
Battery60 MW · 35%
Project Details
State
MS
County
Perry
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Eaton - Lucedale 115 kV Line
Data Source
LBNL
No news available for this project.