— Project Summary

Queue ID
SOCO-IC-932
Capacity
380 MW
Technology
Solar+Battery
Status
active
Location
Glynn, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

380 MW hybrid in Glynn, GA · In queue since December 2020 · Proposed COD July 2024

380 MW

Capacity

2

Components

Solar + Battery

5y 3m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 7m

Schedule

20 months past proposed COD

In Study38%
Queue EntryDec 21, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-07-31

Technology
Solar250 MW · 66%
Battery130 MW · 34%
Project Details

State

GA

County

Glynn

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Thalmann TS 230 kV Bus

Data Source

LBNL

No news available for this project.