158 MW hybrid in Escambia, AL · In queue since January 2021 · Proposed COD June 2024
158 MW
Capacity
2
Components
Solar + Battery
5y 2m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 5m
Schedule
22 months past proposed COD
In Study38%
Queue EntryJan 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Technology
Solar79 MW · 50%
Battery79 MW · 50%
Project Details
State
AL
County
Escambia
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Atmore - Flomaton 115 kV Line
Data Source
LBNL