BetaActiveSolarBatterySOCOLBNL
158 MW hybrid in Dale, AL · In queue since January 2021 · Proposed COD August 2029
158 MW
Capacity
2
Components
Solar + Battery
5y 2m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 7m
Construction75%
Queue EntryJan 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2029-08-15
Technology
Solar79 MW · 50%
Battery79 MW · 50%
Project Details
State
AL
County
Dale
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Enterprise - Pinckard #1 115 kV Line
Data Source
LBNL
No news available for this project.