— Project Summary

Queue ID
SOCO-IC-926
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Montgomery, AL
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarBatterySOCOLBNL

80 MW hybrid in Montgomery, AL · In queue since December 2020 · Proposed COD June 2025

80 MW

Capacity

1

Components

Solar

5y 3m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 6m

Schedule

9 months past proposed COD

Construction75%
Queue EntryDec 16, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-06-15

Project Details

State

AL

County

Montgomery

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Montgomery SS - Snowdoun 230 kV Line

Data Source

LBNL

No news available for this project.