BetaActiveSolarSOCOLBNL
100 MW generation in Newton, MS · In queue since December 2020 · Proposed COD January 2025
100 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 1m
Schedule
15 months past proposed COD
Construction75%
Queue EntryDec 18, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-01-15
Project Details
State
MS
County
Newton
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Collins - Newton 115 kV Line
Data Source
LBNL