— Project Summary

Queue ID
SOCO-IC-922
Capacity
100 MW
Technology
Solar
Status
active
Location
Newton, MS
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

100 MW generation in Newton, MS · In queue since December 2020 · Proposed COD January 2025

100 MW

Capacity

1

Components

Solar

5y 3m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

4y 1m

Schedule

15 months past proposed COD

Construction75%
Queue EntryDec 18, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-01-15

Project Details

State

MS

County

Newton

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Collins - Newton 115 kV Line

Data Source

LBNL

No news available for this project.