BetaActiveSolarBatterySOCOLBNL
160 MW hybrid in Autauga, AL · In queue since November 2020 · Proposed COD November 2024
160 MW
Capacity
2
Components
Solar + Battery
5y 4m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4 years
Schedule
17 months past proposed COD
In Study38%
Queue EntryNov 13, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-01
Technology
Solar80 MW · 50%
Battery80 MW · 50%
Project Details
State
AL
County
Autauga
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
County Line Rd - Gaston 230 kV Line
Data Source
LBNL