BetaActiveSolarBatterySOCOLBNL
150 MW hybrid in Warren, GA · In queue since October 2020 · Proposed COD August 2023
150 MW
Capacity
2
Components
Solar + Battery
5y 5m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 10m
Schedule
32 months past proposed COD
Construction75%
Queue EntryOct 14, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-08-15
Technology
Solar120 MW · 80%
Battery30 MW · 20%
Project Details
State
GA
County
Warren
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Ray Place Road - Warrenton Primary 115 kV Line
Data Source
LBNL
No news available for this project.