BetaActiveSolarSOCOLBNL
220 MW generation in Turner, GA · In queue since October 2020 · Proposed COD June 2023
220 MW
Capacity
1
Components
Solar
5y 5m
In Queue
Suspended
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 8m
Schedule
34 months past proposed COD
In Study38%
Queue EntryOct 9, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
GA
County
Turner
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Tifton - Pitts 230 kV Line
Data Source
LBNL
No news available for this project.