BetaActiveBatterySOCOLBNL
265 MW storage in Cherokee, GA · In queue since October 2020 · Proposed COD January 2026
265 MW
Capacity
1
Components
Battery
5y 5m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 3m
Schedule
2 months past proposed COD
Construction75%
Queue EntryOct 7, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-01-16
Project Details
State
GA
County
Cherokee
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
McGrau Ford Substation 230 kV Bus
Data Source
LBNL
No news available for this project.